CEMENT PLANT SHUTDOWN REPAIRS IN USA. CEMEX, ASH GROVE, TITAN. MARCH-APRIL-MAY 2024. USA.
During the months of March, April and May 2024, repairs were carried out in different plants of the USA, such as Brooksville, Miami, Seattle, Sumterville, Medley and Texas. For these works we supplied more than 600 t of dense castables and 20 t of insulating castables.
The installation was carried out by US contractors and, as usual, we provided the technical supervision, once again highlighting the performance of our castables.
Location
USA
Date
March-April-May 2024
Sector
Cement
Speciality
Refractory