The project included mechanical refurbishment, robotic demolition, surface preparation, anchor installation and refractory lining installation using several techniques. The work covered the burner, kiln outlet and inlet, stage 3 cyclone, calciner, lower riser duct and cooler.
The shutdown was completed with zero accidents, according to the project report. More than 50 safety briefings were held at the start of work shifts.
Refractory lining replacement at the burner and kiln outlet
The main burner was lined with DRYTECH 95 at the tip and DRYTECH 85 on the body, with a lining thickness of four inches. The team removed the existing lining, welded the anchors and set up the formwork before installing the new lining.
The kiln outlet ring was lined with DRYTECH 40 SIC. The installation included ceramic and metal anchors, prefabricated formwork and expansion joints.

Mechanical and refractory refurbishment of the stage 3 cyclone and riser
A major part of the project was relining the stage 3 cyclone, where the team installed 55 metric tons of refractory bricks. The team used bricks and monolithic refractories in different areas of the cyclone.
The mechanical work included completely replacing a 10-meter-high section around the full circumference of the riser, as well as replacing the cone and part of the cylindrical section of the stage 3 cyclone. This work was coordinated with the replacement of the refractory linings in the same equipment.

The calciner and lower riser duct were lined with AJ PUMP ABR CLEAN + and ABR CLEAN +. The work also included mechanical refurbishment, insulation and formwork preparation.
ALFRAN materials at the kiln inlet and cooler
The project also covered several areas of the kiln inlet, where materials from the ABR CLEAN range were used, including ABR CLEAN SUPER +, ABR CLEAN + and AJ PUMP ABR CLEAN +.
In the cooler , work covered the walls, roof and other areas. Materials included AJ PUMP DRYTECH CLEAN 60, which was applied to one of the side areas of the first drive section.
Robotic demolition and safety during the maintenance shutdown
EZ Refractories used Brokk equipment in several areas of the plant. Inside the kiln, the remotely controlled Brokk 200 allowed the operator to carry out demolition from a distance.
Safety was a priority throughout the shutdown. The more than 50 safety briefings covered work permits, personal protective equipment, energy isolation, working at height, confined spaces and lifting operations.
Completing the work with zero accidents was one of the key outcomes of the project.
ALFRAN and EZ Refractories: Working together on cement plant maintenance
The Cemex Miami project brought together ALFRAN as the materials supplier and EZ Refractories as the installer during a shutdown that combined mechanical refurbishment with refractory maintenance.
From the burner to the cooler, the project brought together refractory materials, installation techniques and robotic demolition equipment to renew the linings during the 2026 K1 shutdown.