SUPPLY AND INSTALLATION OF PASSIVE FIRE PROTECTION IN ALL MODULAR STRUCTURES

Installation of Pyrocrete material in all modular structures.

Project with an approximate duration of 18 months that was developed in the SH port facilities in the port of Tarragona and was completed at the Exxon-Mobil facilities in Antwerp (Belgium). Alfran adapted its operative capacity to the demanding planning of the client which led us to count up to 120 workers in the project. In the execution of this project, FLUOR, a world leader in the implementation of prevention systems, has been able to verify the high safety standards of Alfran.

Global magnitudes

Structure surface: 19,900 m2

Average staff: 50 operators

Duration: 18 months

Total project hours: 97,000 hours

By clicking here you can consult a related project, which was carried out in the same facilities.

Location

Tarragona, Spain and Antwerp, Belgium

Date

2015 – 2016

Sector

Oil & Gas

Speciality

Fire-Proofing