SUPPLY AND INSTALLATION OF THERMAL INSULATION IN THE COKE UNIT

Thermal, acoustic insulation using rock wool and high performance materials such as Pyrogel. A total of 30,000m2 of pipes and 2,000m2 of equipment. Project with an approximate duration of 18 months that was developed in the SH port facilities in the port of Tarragona and was completed at the Exxon-Mobil facilities in Antwerp (Belgium). Alfran adapted its operative capacity to the demanding planning of the client which led us to count up to 120 workers in the project. In the execution of this project, FLUOR, a world leader in the implementation of prevention systems, has been able to verify the high safety standards of Alfran.

Global magnitudes

Surface of pipes: 30,000 m2

Surface of equipment: 2,000 m2

Average staff: 50 operators

Duration: 18 months

Total hours project: 98,000

By clicking here you can consult a related project carried out in the same facilities.

Location

Tarragona, Spain and Antwerp, Belgium

Date

2016 – 2017

Sector

Oil & Gas

Speciality

Insulation