Alfran Saudi Arabia has been awarded a contract with the cement company or Arabia, Rabigh-KSA, for the installation of refractory lining in the precalciner of line 6.
The total area covered was 200 m2. The total duration of the work was 13 days, starting on April 11 and ending on the 22nd of the same month. The scope of these included demolition, anchoring and installation of dense concrete by shotcreting.
A large part of the mechanical work was carried out during the same period. It included the manufacture and installation of almost 150 m2 of sheets, which were completely damaged, in the conical section of the precalciner. Likewise, substitution by burner lances was carried out. The mechanical work was carried out by Arabian Cement.
ASA installed a total of 60 Tm of Alfranjet 45 SIC and 15 TM of Alfranlite 10-14 Li.
The works were in charge of the Operations Manager of ASA. They were carried out with a total of 28 workers, 24 locals and 4 technicians, who were from Alfran Spain.
Arabian Cement was very satisfied with the work developed by Alfran.





This platform replaces the old Abkatun Alfa. That one suffered an appalling fire in April 2015. Regarding Abkabun A-II, it is expected to have a daily production of 200.00 barrels. It will be located in the Abkatún-Pol-Chuc field, operated by Pemex, in the Campeche basin, between the states of Campeche and Tabasco, and about 132km northeast of the port of Dos Bocas.

It is a strategic contract in which it has been necessary an excellent work of several departments. This is how we manage to make a competitive offer technically and economically. A 5-year contract, which reinforces our position as a reference supplier for Arcelor Mittal.